How to Build a Crawl Space Footing: 240 lb of Concrete in One Pour
My crawl space has a sagging beam, and before I could put a jack post under it I needed a solid concrete footing. I had already dug an 18-inch-deep hole, so in this video I set the rebar and the form, then mixed and poured 240 pounds of concrete right there in the crawl space. It almost went wrong when my mixing tub cracked under the weight.
I’m a homeowner, not a contractor, and this is simply my experience. Check your local code for footing requirements, follow at your own risk, and use proper safety precautions.
Before You Begin: Plan to Pour in One Go
Have everything ready before you open the first bag. My plan was to pour the footing in one go, so the rebar, the form and the backfill all had to be in place first. I also decided to mix right next to the hole instead of mixing outside and carrying heavy concrete into the crawl space.
Make sure your mixing container can take the weight. Mine couldn’t, and that’s the part of the video where things nearly went sideways.
Tools You’ll Need
- Shovels (a smaller one helps you hit the form accurately)
- Rebar (I used a 10-foot section plus another piece) and tie wire
- A few bricks to raise the rebar off the bottom
- Concrete form
- Level
- Tamper
- Pebbles/gravel for the bottom of the hole and rocks for backfill
- Bags of concrete (I bought four 80 lb bags and used three)
- A sturdy mixing container, plus a couple of 2x4s in case it needs support
- Knife to open the bags, and a container to measure water
- Hammer
Step 1: Level the Bottom of the Hole
The hole was about 18 inches deep. I put some pebbles in the bottom, checked that it was fairly even, and tamped it down. Don’t worry about making it perfect, but you want a stable, level base.
Step 2: Build and Set the Rebar Frame
I tied the rebar together with wire to make a frame, then attached vertical pieces so the reinforcement would run up into the column. I set it on a couple of bricks so it sits up off the bottom of the hole and won’t budge.
Step 3: Position the Form Under the Beam
Next the form goes in on top. I made sure the top was even in both directions and, most importantly, that it was centered under the beam. This is also where I changed my plan: instead of adding a second column on top, I realized the adjustable jack post could be lowered enough to stand right on the footing.
Step 4: Backfill Around the Form
With everything centered, I backfilled around the form with a lot of rocks to lock it in place. Once it was holding up well, I was ready to pour.
Step 5: Mix the Concrete Next to the Pour
Three 80 lb bags is 240 pounds of concrete, so I mixed it right next to the hole. Partway through, my plastic mixing container cracked under the weight. I slid two 2×4 boards underneath to support it, mixed two bags first and then added more. Make a hole in the middle for the water and add it gradually, following the instructions on your bags.
Step 6: Fill the Form and Settle the Concrete
I shoveled the concrete into the form, switching to a smaller shovel to hit the opening accurately, and worked it into the voids. I noticed that tapping on the form with a hammer helped the concrete settle, so I kept doing that and checked the level as I went. I had about half a bag left, so that went in too.
Step 7: Smooth the Top and Let It Cure
Finally I sealed and smoothed the top as best I could and left the footing to cure. A few weeks later I set the jack post on it, lubricated the thread and started adjusting it slowly to take up some of the load. There’s no rush with that part.
Final Thoughts
Pouring a footing in a crawl space is hard work, and respect to the professionals who do this every day. The big lesson for me: use a mixing container that can actually take the weight, or support it from the start. You can see the full jack post installation in my jack post video, and how I dug this hole in Is This Deep Enough?.